These example charts show that scope (in terms of Stories) may expand or contract as new discoveries are made and work is reprioritized. The projected rate of progress through the Stories - that is, how quickly the team is expected to render business needs code complete - is rooted in a simple formula that includes capacity, distraction management, and estimate weight (complexity, etc.) relative to the team.
By tracking progress through Stories, we're measuring accomplishment of meaningful results. With each iteration, the PMO knows the specific functionality that an asset possesses and how much it cost to get it to that point. We also know what functionality the asset does not have and we have a pretty good means by which to forecast how much it's going to cost to complete that functionality. Best of all, in near real-time we can see if a project is showing signs of trouble, we can see almost immediately the impact of changes that we make, and we can communicate all of this in business (as opposed to IT) terms. Traditional IT cannot provide this level of transparency.
The burn-up is meaningful only if we know that it has integrity. Nothing prevents us from defining and tracking technical tasks. If we do that, we're really no better off than we are in current IT practices: it’s just a burn-up of effort, but not of results achieved. We have to make sure teams are relentlessly focused on satisfying business need, from the time a requirement is captured to the time software is certified as production ready. By writing well formed Stories, we're writing the "completion gene" into the DNA of a project team. This aligns the interests of the business (the buyer), the PMO (the buyer's agent and de-facto underwriter), and the development team.
This gives us direct line-of-sight from the unit of measurable work all the way through to the project reporting level, so that when we report upward we know that there is integrity in what we’re reporting. This is deceptively simple, but is the critical component to the Agile PMO: we know what is done, and what isn’t done, not in IT terms but in the terms of what it is we're buying. By extension, we know our investment yield to date and what returns further investment will yield.
The proliferation of Agile Project Management tools, such as Mingle from ThoughtWorks Studios, make it far easier for the PMO to get project performance data from in-flight projects. We don't need to transcribe data from what a PM has told us into what the project sponsors need to know. We're not e-mailing spreadsheets around. We're drilling into a project dashboard to see what’s going on, and we know what’s going on in very granular terms that relate back to the state of the asset.
The combination of team organization and Story-based requirements allow us to work and measure in terms of results. But the results we're looking for go beyond “completed Stories.” We must also have some appreciation for the quality of the solution delivered. Progress – even in “functionality” terms – may be completely hollow if the expected level of quality (e.g., maintainability, technical quality, etc.) isn’t baked in at the same time. This means we are at risk of over-stating our results. In our next installment we’ll have a look at how we can align quality metrics to get a complete picture of solutions delivered, and we’ll look at how to automate capture to make this simple. Once we’ve done that, we’ve defined the fundamental tools necessary for an Agile PMO.
1 Hollinger, Peggy."In a tangle: How having to wire the A380 by Hand is hampering Airbus." Financial Times. 16 July 2008.